115kv 67MVA Transformer
1.Erection takes total 8 days with 15 man power
2.Vaccuming of main tank take 3 days upto -0.5tar
3.Oil circulation 3 days
4.Oil Filling and setteling 1 days
=8+3+3+1=15 days / Transformer