OUTAGE WRIT UP



OUTAGE WRIT UP 

  1. Read the PTS  

a.       Scope of work
b.       Number of panels
c.        Additional card for SCADA, SOE, Annu, DFR

  1. Site Visit
1.       Collect all IFC drawings from existing station
2.       Collect all existing  point list
3.       Check cable rote length for fiber & control cables & Power cables

  1. Materials
1.       Check the availability of all Control & Power & Fiber optic  cables and cable hose
2.       Check Ferule Machine and tap
3.       Check Lugs
4.       Check panels and find the missing materials before outage
5.       Check the loose materials
6.       Check all communication materials ( Optif , SFT ect)

  1. Point list
              SAS, SACDA, SOE, Annu, DFR

1.       Check all New point list IFC
2.       Before Outage, discuss with SCADA deportment for using the spare points through PMD
3.       Submit the RFI and Point list to SCDA deportment soft & Hard copy and conform the witness.
4.       Check SAS engineer Iquma & He should be direct employ of the company otherwise SAS Vendor should give the letter with proper note pad and stamp ( Strict order from SCADA deportment ) .
5.       Don’t do existing Measurement points, Transducer will make issue.
6.       After open loop submit the points to SCADA & PCC for SAS close loop or SCADA final commissioning
7.       Conform the PCC witness & SCADA witness & SCADA vendor for final commissioning.

  1. Vendor follow ups

1.       Check the PO for all Vendors
2.       Send mail for vendors SAS , SCADA, SOE, DFR and Fault locator , AMI , Fiber optic testing team.
3.       Check SEC ID
4.       Collect Iqama copy from vendor
5.       Collect all PO copies for Temporary access.
6.       Collect laptop details for Temporary access.

  1.  Testing activities
1.        Don’t touch the Protection panels without getting permission from PCC
2.       Whenever touch existing panel inform PED.
3.       Testing agency engineer SEC ID , Testing Approval
4.        Testing Team - Panel wiring , Relay configuration, Aux relays , Schemes
5.       First time CSD 3 week schedule  send through PMD
6.       Get the signature in  all drawings CSD & Testing engineers
7.       LCC access make LOA for GIS witness
8.       Tripping test make separate  LOA 
9.       SCADA & SAS Make separate LOA
10.    CSD – Pre commissioning check list should be fill
11.    Reserve the Testing engineers & SAS engineers for commissioning activity



7. Communication

                1. Send Channel request for Fault Locator & AMI & PSE Differential protection with SLD & Communication drawing
                2. Coordinate with NEC or ABB for get updated communication drawing and communication link
                3. Coordinate with NEC or ABB for Optif card installation check SFP converter its dB range (If applicable).
                4. Apply communication accesses and follow with communication deportment and make communication LOA with approved access.
5.       Laying Fiber , RJ45, Bueldon cable.
6.       2 Mpbs Micom 546 need Baloon converter and coaxial cable .
7.       Proper soldering need for coaxial cable and cable connector to avoid differential communication fail.
8.       Check all cables, orange hose , cable rote , cable rope for tie, small boot lugs , channel allocation table from NEC, communication drawings, LOA approved copy, communication access copy.
9.       Include Fiber optic testing in the communication LOA.

8. Documents submission 

  1. Submit one soft copy  CD to PMD & P TD
  2. Submit one soft copy  HARD DISC to CSD
  3. Updated point list to SCADA
  4. All documents submit through proper submittal with Delivery Note