Substation Testing and Commissioning

Sunday, April 29, 2012

›
HV TEST FOR 230 KV GIS  High Voltage level of injection is below  Highest voltage level 380 kv is calculated from 80% of factory ...
Thursday, April 26, 2012

›
THE STORY OF TRANSFORMER STABILITY The transformer stability test used to conform the CT connections for Differential and REF protect...
Thursday, April 5, 2012

TIMINGS & TIME SETTINGS

›
Saturday, March 24, 2012

ABTS LOGIC

›
ABTS logic truth table for two transformer arrangement Closing Logic Tripping Logic Note:- ABTS Block 1. Transformer Timed Over current Trip...
Tuesday, March 13, 2012

INTER LOCK FOR TRANSFORMER HI & LOW SIDE INCOMER

›
LOW SIDE CB RACK IN BLOCK 1.Low Side Inter locks 1.1 CB Aux Contact - CB should be open Condition 1.2 Bus Earth & feeder line side switc...
‹
›