Substation Testing and Commissioning

Friday, May 14, 2010

CABLE LAYING

›
BEFORE CABLE LAYING 1.There are two schedules a. Laying schedule b. Termination Schedule 2.Seperate the laying schedule i...
Tuesday, May 4, 2010

PROG

›
This is book PROG is very useful for every T & C Engineer 00 Application Tables 01 INTRODUCTION 02 Fundamentals 03 Fundamental Theory 04...
Monday, May 3, 2010

THE DISMANTLED PANELS

›
HOW TO HANDOVER THE DISMANTLED PANELS TO SEC-EOA 1. Take the list of Dismantled materials 2. Go to SEC and meet the particular departme...
Friday, February 5, 2010

ABU HADRIYAH BSP

›
Protection bay C2 (A804,A805,A806) Distance protection 1.Fault current enter side should be CT P1 2.If 1 1/2 scheme CT's cover both brea...
‹