Monday, June 20, 2016
MAIN ACDB INTERLOCK ISSUE
Generally the contacts used for interlocks should be direct or high speed contacts. We faced a problem in Main AC distribution panel.
Auto transfer scheme ( ATS)
As per ATS scheme consider incomer CB trip due fault then Bus tie should not close in both Automatically or manually.
Same condition if Bus tie trips incomers should not close in both Auto/Manual condition.
Problem faced Site:
1. Both Incomers are closed and Healthy. Incomer -1 tripped by jumper and tie was automatically not closed. But trip was given by actual current injection and bus tie closed.
2. Now Incomer -1 and bus tie is closed and Bus tie tripped by jumper and Incomer -2 was automatically not closed. But trip was given by actual current injection Incomer -2 closed.
Same happen for Incomer -2 and Bus tie combination.
The breaker trip Aux. contact is in serious of other Breaker closing path. This contact should immediately open and block the other CB closing.
But in our circuit tripping Aux contact will pick up a auxiliary relay and this relay contact open the other CB closing path. But pickup time of this relay is little bet high . During this pick up time adjesend CB was closed.
So found that problem and replace high speed Aux relay.
Auto transfer scheme ( ATS)
As per ATS scheme consider incomer CB trip due fault then Bus tie should not close in both Automatically or manually.
Same condition if Bus tie trips incomers should not close in both Auto/Manual condition.
Problem faced Site:
1. Both Incomers are closed and Healthy. Incomer -1 tripped by jumper and tie was automatically not closed. But trip was given by actual current injection and bus tie closed.
2. Now Incomer -1 and bus tie is closed and Bus tie tripped by jumper and Incomer -2 was automatically not closed. But trip was given by actual current injection Incomer -2 closed.
Same happen for Incomer -2 and Bus tie combination.
The breaker trip Aux. contact is in serious of other Breaker closing path. This contact should immediately open and block the other CB closing.
But in our circuit tripping Aux contact will pick up a auxiliary relay and this relay contact open the other CB closing path. But pickup time of this relay is little bet high . During this pick up time adjesend CB was closed.
So found that problem and replace high speed Aux relay.
Wednesday, June 15, 2016
Battery Bank Recharging Problem
The battery System have 58 Cells and nominal voltage will be 125V DC. One day the 380 Volts Battery charger input AC supply was tripped and load was taken from battery bank.
The system voltage was reduced up to 90 V DC .
The 380 V AC MCB was reset and Battery start to charge again and drown 450 Amps.
Normally this current should gradually reduce to normal value 70 -80 Amps. But 450 Amps continuous for 4 ,5 hours. The cooling system alarm fail was appeared.
We arranged extra fans around the Charger. With in half-an hour current start to reduce gradually and become normal value.
The system voltage was reduced up to 90 V DC .
The 380 V AC MCB was reset and Battery start to charge again and drown 450 Amps.
Normally this current should gradually reduce to normal value 70 -80 Amps. But 450 Amps continuous for 4 ,5 hours. The cooling system alarm fail was appeared.
We arranged extra fans around the Charger. With in half-an hour current start to reduce gradually and become normal value.
Saturday, June 11, 2016
RED 670 TEST PROCEDURE BY Mr.OMER
Mr. Omer is by best friend presently working in XERVON - Saudi
He write a best article about How to test the Differential Relay RED 670.
He is given this article free for beginners.
Link to download
Note : I hope your not miss use this article
He write a best article about How to test the Differential Relay RED 670.
He is given this article free for beginners.
Link to download
Note : I hope your not miss use this article
TRANSFORMER HV BUSHING PF VALUE
Make : CG Transformer
Rating : 67 MVA - 380/115/13.8kV
The Power factor value HV side bushing should be below 0.5%.
But during our testing the value came around 1.45%.
Our Transformer Fourmen top bushing. The bushing is connected with flexible conductor and immersed with the oil. He tight this connection and clean the area around.
We conduct again same test and result is with in the limit 0.3%.
HV busing
Test value after tight and clean