Monday, April 25, 2011
END TO END TEST
END TO END TEST
1.The sending and receiving of datas from one end to other end is very importent in line protection
2.The Protection Signalling Equipment (PSE) is used in between both end protection panels.
3. Four main tripping signals are send and receive a) Distance protection b) Directional Earth Fault(DEF) c) Pole descripency second stage d) Breaker Failure second stage
Thursday, April 14, 2011
FOIP CONNECTIONS
Line diffrential protection
Relay to FOIP panel and FOIP to communication panel connection Drawing
Relay to FOIP panel and FOIP to communication panel connection Drawing
TIMINGS
1. 380 kv breaker tripping time 14 -15 ms and closing time 78-79 ms
2. Breaker coil current a. Closing coil current 5-6 Amps b. Tripping coil current 13-14.5 Amps
3. PD first stage timeing 500 ms second stage 2.5 s
4. Breaker Filure first stage timeing 100 ms second stage 200 ms
2. Breaker coil current a. Closing coil current 5-6 Amps b. Tripping coil current 13-14.5 Amps
3. PD first stage timeing 500 ms second stage 2.5 s
4. Breaker Filure first stage timeing 100 ms second stage 200 ms
Monday, April 4, 2011
Test reports for 380 KV substation