Saturday, December 31, 2011

BUSBAR PROTECTION TRIP

1.In transformer feeder busbar protection will operate both the High side breaker and
lower side breaker

2.BF stage -1 and BB protection will initiate TC1 & TC2 of all breakers.

MICOM 142 DOCR TRIPPING CONDITION

Relay will trip single phase faults reference with other phase voltage

For three phase fault relay will take last one min memorised RYB voltage.

If one hour maintenance shout down memory voltage will errised then any bady switch on the CB with three fault there is no voltage in memory and relay will not operate for this fault.But in Line protection relay SOTF will operate.

Tuesday, December 27, 2011

RED 500 to DTR CONNECTION

RED 500 to DTR RJ pin connection (1 2 3 4 5 6) to ( 3 6 1 4 5 2 )

SCADA & SOE PAIR CABLE

Pair cable shield wire should be grounded at one side for Analog points
to avoid the error in the reading and out side noises effects.

Monday, December 26, 2011

HI - POT LEAKAGE CURRENT

How to calculate the Hi-pot leakage Current?

I = U X 2пcf

U = Applied voltage
c = Total capacitance = Instrument Capacitance + Circuit Capacitance
f = Frequency applied = 1/2п√CL

Note: Circuit Capacitance can measure with IR value measurement kit.

Saturday, December 24, 2011

VACUUM IS A CONDACTOR

Vacuum will become a conductor in some potential stage.So don't do any
electrical test in equipment

CT CONNECTION TIPS

CT CONNECTION TIPS

1.For Bus section and Bus coupler The CT "P1" should be Breaker Side

Saturday, December 17, 2011

CT METERING CORE STAR POINT

CT Star point connection for metering core should be towards line or cable or transformer side.

In energy meter IMPORT reading should be -ve sign
EXPORT reading should be +ve sign

In line feeder power towards bus and current develop 180 dec displaced and
Energy meter shows -ve reading.(Power inter in earthing point side P2 side)

In cable feeder power outwards to bus and current develop 0 dec displaced and
Energy meter shows +ve reading.(Power inter in side P1 side)

Monday, November 21, 2011

REF HIGH IMPEDANCE SETTING

To have high sensitivity for Transformer REF protection Transformer REF setting as 10% 0r 15% or less. Transformer REF setting may not be more than 20%.

DSM REQUIREMENT

1.IP Address

2.Subnet Mask

3.Default Gateway

4.HAND OVER BOOK


Saturday, November 12, 2011

HI POT TEST TIPS

1. Before IR value test remove the VT primary neutral and reconnect during HV test.
2. Remove the line capacitance primary links
3. Short all CT secondary

Saturday, September 17, 2011

IEC CODES

1.IEC 60027 Letter symbols to be used in electrical technology...
4.IEC 60044 Instrument transformers
7.IEC 60063 Preferred number series for resistors and capacitors
8.IEC 60065 Audio, video and similar electronic apparatus - Safety requirements
9.IEC 60068 Environmental Testing
10.IEC 60071 Insulation Co-ordination
11.IEC 60073 Basic Safety principles for man-machine interface, marking and identification
14.IEC 60085 Electrical insulation
16.IEC 60099 Surge arresters
17.IEC 60134 Absolute maximum and design ratings of tube and semiconductor devices
18.IEC 60137 Bushings for alternating voltages above 1000V
19.IEC 60146 Semiconductor Converters
20.IEC 60169 Radio-frequency connectors
21.IEC 60183 Guide to the selection of high voltage cables
22.IEC 60204 Safety of machinery
23.IEC 60214 On-load tap changers
25.IEC 60233 Tests on Hollow Insulators for use in Electrical Equipment
26.IEC 60238 Edison screw lampholders
27.IEC 60245 Rubber-Insulated Cables
28.IEC 60255 Electrical Relays
29.IEC 60268 Sound system equipment
30.IEC 60269 Low voltage fuses
31.IEC 60270 High-Voltage Test Techniques - Partial Discharge Measurements
32.IEC 60287 Calculation of permissible current in cables at steady state rating
33.IEC 60092-350 Shipboard Power cables-General construction and Test Requirements
34. IEC 60296 Mineral Insulating oils for transformers & switchgear
35.IEC 60298 high voltage switchgear in metallic enclosure
37.IEC 60317 Specifications for particular types of winding wires
39.IEC 60331 Tests for Electric Cables under Fire Conditions
42.IEC 60417 Graphical symbols for use on equipment
43. IEC 60439 Low voltage switchgear and controlgear assemblies
44.IEC 60445 Basic and safety principles for man-machine interface
45. IEC 60446 Wiring colours
46.IEC 60479 Effects of current on human beings and livestock
47.IEC 60502 Power cables with extruded insulation and their accessories for rated voltages from 1KV up to 30KV
50.IEC 60529 Degrees of protection provided by enclosures (IP Code)
51.IEC 60598 Luminaires
52. IEC 60559 Binary floating-point arithmetic for microprocessor systems
54.IEC 60603 Connectors for frequencies below 3 MHz for use with printed boards
55.IEC 60617 Graphical symbols for diagrams IEC 60651 Sound level meters
56.IEC 60694 Common Specifications For High-Voltage Switchgear and Controlgear Standards
57.IEC 60715 Dimensions of low-voltage switchgear and controlgear. Standardised mounting on rails for mechanical support of electrical devices in switchgear and controlgear installations.
58.IEC 60721 Classification of environmental conditions IEC 60726 Dry type power
transformers IEC 60747 Semiconductor devices; Part 1: General
59.IEC 60748 Semiconductor devices - integrated circuits
60.IEC 60774 VHS/S-VHS video tape cassette system
62.IEC 60801(part 3) EMI and RFI Immunity
63.IEC 60812 International Standard on Fault Mode and Effects Analysis
64.IEC 60815 Selection and dimensioning of high-voltage insulators intended for use in polluted conditions
65.IEC 60874 Connectors for optical fibres
66.IEC 60884 Plugs and socket-outlets for household and similar purposes
68.IEC 60906 IEC system of plugs and socket-outlets for household and similar purposes
69.IEC 60908 Compact disk digital audio system
70.IEC 60921 Ballasts for tubular fluorescent lamps - Performance requirements
71.IEC 60929 AC-supplied electronic ballasts for tubular fluorescent lamps - Performance requirements
72.IEC 60947 Standards for low-voltage switch gear and controlgear
73.IEC 60950 Safety of information technology equipment
74.IEC 61000 Electromagnetic compatibility (EMC)
75.IEC 61009 Residual current operated circuit breakers with integral over current protection for household and similar uses (RCBO's)
76.IEC 61010 Safety requirements for electrical equipment for measurement, control and laboratory use
79.IEC 61131 Programmable Logic Controllers.
80.IEC 61156 Multicore and symmetrical pair/qud cables for digital communications
82.IEC 61238, Compression and mechanical connectors for power cables for rated voltages up to 30 kV
83.IEC 61280 Field testing method for measuring single mode fibre optic cable
84.IEC 61286 Character set with electrotechnical symbols
85.IEC 61326 Electrical equipment for measurement, control and laboratory use - EMC
requirements
86.IEC 61378 Converter Transformers
87.IEC 61400 Wind turbines
88.IEC 61439 Low-Voltage switch gear and controlgear assemblies
89.IEC 61499 Function blocksDownload: eType1.com/f.php?FurInf
90.IEC 61537 Cable management - Cable tray systems and cable ladder systems
91.IEC 61557 Equipment for measuring electrical safety in low-voltage distribution systems
99.IEC 61642 Industrial a.c. Networks Affected by Harmonics - Application of Filters and Shunt
Capacitors
100.IEC 61643 Surge protective devices connected to low-voltage power distribution systems
101.IEC 61672 Electroacoustics – Sound level meters
102.IEC 61753 Fibre optic interconnecting devices and passive components performance
standard IEC 61784 Industrial communication networks - Profiles
103.IEC 61800 Adjustable speed electrical power drive systems
104.IEC 61803 Determination of power losses in high-voltage direct current (HVDC) converter
stations
105.IEC 61829, Crystalline silicon photovoltaic (PV) array - On-site measurement of I-V
characteristics
106.IEC 62262 Degrees of protection provided by enclosures for electrical equipment against
external mechanical impacts (IK code)
107.IEC 62271 Standards for high-voltage switchgear and controlgear

Sunday, August 28, 2011

BASICS OF ELECTRICAL

ATOMS

All meters (solid, Liquid, Gas) are composed by minute particals called Malicules. There are two part in Atom, 1. Nucleus 2.Extra Nucleus

a. Nucleus

The Nucleus contains Protons and Neutrons

Protons are positively charged particals and Neutrons have no particals

b.Extra Nucleus

Extra Nucleus contain only Electrons

Electrons are negatively charged particals and moves around the Molicules with different orbits.

The number of Protons are equels to Number of electrons in an Atom.

Atomic Wieght = No. of Protons + No. of Neutrons

Atomic Number = No. of Protons or No. of Electrons

Normally the Number of Protons and Number of electrons are equles in a body. So the resultant charge is zero and the body electrically neutral.

Charge

The charge is Electrical energy possessed by protons or Electrons in an Atoms

Unlike charges attract each other and like charges or repels each other.

The Law of Conservation

The Law of Concervation stats the algebraic sum of chares remain constant in a closed path. Therefore the charge can neither be created nor be distorted.

The unit of the charge

The charge on an electron is so small that is not convenient to select it as the unit charge. Normally Coulomb is the unit of charge. One Coulomb is equal to the charge on 6.28 X electrons.

Each protons has positive charge = 1.6 X C.

If 6.28 X Electrons remove from a neutral body then the body as positive charge 1 coulomb.

If we say that a body has a negative charge of 1 C we should remove 6.28 X electrons from that body.

Coulomb Inverse square Law

The force two point charges is directly proportional to product of the two charges and inversely proportional to square of distance between two charges.

F = 1/4π q1q2/

r - Distance between two charges

ε0 – The permittivity of free space

ε0 – 8.514

If charge placed in a material then

Permittivity = ε0 εr

εr – Relative permittivity of the material

Electric Field

The space around the charge in which the influence is felt is known as Electric field.

Electric field Intensity

The force experienced by an unit coulomb charge called Electric field Intensity.

E = F/q

F – Force in Newton

q – Charge in Coulomb

CURRENT AND VOLTAGE

American physicists TOLMAN and STEWART experimentally con formed that the electric current in a conductor is a carried by electrons. The electrons in outer most orbit will less bound with nucleus and called free electrons. The free electrons move at random from one atom to other atom in the materials.

Electro Motive Force

An external force necessary to move the free electrons in definite direction is called Electro Motive Force.

Faradays Law

When ever a conductor cut the magnatic field an E.M.F induced in the conductor.

E.M.F = BAL sinθ

B – Magnatic density in webber

A – Area of the conductor

L – Length of the conductor.

Theory of current (The Machanism of flow of current )

A metal piece contain a large number of free electrons moving in randam directin. The maxiumam speed the free electrons in the order of m/s. Due to e.m.f the electrons get accelerated and move in a definite direction. Due to electric field of moving electrons the electrons in the closed circuit also get accelerated and start to move.

The direction of moving electrons can be find by Flamings Right hand rule.

If E is the strength of the electric field applied from conductor closed circuit then the force on the electrons in the closed conductor

F = e.E

e- The charge on electrons in closed circuit.

The acceleration produced on on electrons in a closed circuit

a = F/m m – Mass of the electrons a = eE / m

Due to acceleration the velocity of an electron increase but happens only short time τ.

The electrons in a closed circuit contain The additional velocity acquired from e.m.f for τ time is called DRIFT VELOCITY.

Vd = a τ =( eE / m) τ.

Consider a wire of cross section ‘A’. Let ‘n’ be the number of free electrons per unit volume. The free electrons moves towards left with a constant drift velocity Vd.

Numer of free electrons passed through the area of cross section per unit time = nAVd. Therefore the charge that flows per unit time = nAVde. This also called the current flows through the wire I= nAVde.

This is relation between current and velocity

I= nA E τ/ m.

Electric current

The rate of follow of charge in any cross section of a wire is defined as the electric current.

I = Total charge flowing in a cross section / Time taken

If charge dq flows through a wire in small time dt. The electric current = dq / dt.

The unit of current is Ampere.

One coulomb of charge flow through the wire in one second is called one Ampere.

One ampere = 1 coulomb of charge (c) / 1 second (s) = 1

If there is no changes in rate of change of current and rate of change of time the the current is called steady current and if any one or both frequently change then the current called Alternating current .





Theory of Potential different

Consider a body in that one coulomb of negative charge is removed

Now the body is called positively charged body. Certain work was done to charge the body and it is stored in the body as potential energy.

AUTO RECLOSE

Auto Reclose Blocking Scheme
1. AR shall not be intiated under line is connected with generator bus unless proper analizes in the fulty line.
2. In case genarating power plant bus is connected to grid by medium and long lines,high-speed auto reclosing can be intiated by reverse direction (first chargeing the line from remote end and then reclose the CB at power plant end) for lines which restict the fult current to such a level that maximum shaft torques are with in the genarator specification under fault conditions.
3. AR shall not be intiated under the following conditions
a. BFP, BB protection trips
b. Direct transfer receiving Trips ( BF,PD)
c. SOTF Trips
d. Time delay trip
e. All type of communication failures ( 21 , 87L, BF,PD)
f. Both line & Bus side VT fuse failures

AR operate only zone -1 Ground to Earth Fault

Monday, August 22, 2011

Testing Tips CT

CT Testing

1. When your test the CT with CT analyzer remove the Metrosil connections.
Otherwise analyzer will show the more Ratio error and class fail.

2. Some ring type CT's core are connected with bus voltage. Take more care on dressing the wires.This wires are connect with RYB three phases.Therefore wires should be separate with appropriate air gap.

Tuesday, August 16, 2011

Monday, August 15, 2011

SEC STANDERS ON CONTROL PANEL

1. Panel size should be 800 (W) X 800 (B) X 2200 (H)

2. Aux Power supply 127 V (AC), 220 V (AC) , 125 V (DC)

3.Group of terminals should identified by engraving labels.

4.The distance between TB and race way should be 80mm.

5. 10% spare terminals should provide.

6. The bottom of any relay and test block shall not be less than 300mm from floor level.

7. Not more then 2 LOR in the row and 15 cm between lockout and 10mm other relays.

8.VT secondary should ground at CVT junction box and CT secondary should ground at first interning point of protection panel. For metering CT secondary grounding at control panel.

9. Wiring size a) CT and VT and less than 2.5 Sq mm b) SCADA , SOE, ANNU not less than 0.8 Sqmm c) SCADA control output signal and other control wires not less then 1.5 Sq mm.

Saturday, August 13, 2011

DESIGN TIP GIS

Inter lock bypass key should not bypass the SF6 minimum operating pressure interlock

Friday, August 12, 2011

DESIGN TIP BF II STAGE

1. The BF second stage (86BF) no need to use in close block circuit because breaker already trouble to open. Breaker 'b' contact already serious in closing circuit if breaker is in open condition it will not allow the closing command to CB.

2. The trip setting of Tie breaker should be less then the trip setting of other to Incomers

Because if any fault on tie breaker side then Tie breaker should trip first and save the incomer voltage.

Thursday, August 11, 2011

Design Tip AUX RELAYS

TIMING FOR AUXILIARY RELAYS

1. High speed relay used for SOE, TFR 1ms
2. Other signals ANNU, SCADA 4 ms
3. BF initiation timers ( 0 - 100 ms)
4. High speed 85 DTTR, 85 PD relays 4 ms
5. DC supervision relays 100 ms

Design Tip AR BLOCK

Why 94BF -1, 86 BF -2 trip no need to block the AR relay ?

The breaker status contact is given to AR relay to monitor the breaker.
AR relay give the close command if CB is in open condition.

Breaker failure operate means CB in closed condition and failure to open for trip command.

AR relay automatically blocked when the CB is in closed condition.

Therefore separate close block no need from 94BF -1, 86 BF -2.

Transformer Protections

Transformer Protections
1. Transformer diffential protection
2. REF HV, REF LV
3. Dir O/C HV, LV , HVN, LVN (IOC, TOC) ,
4. O/C HV and LV Grounding
5. Mechanical Trip
a.BUZ relay Main Tank
b.BUZ relay OLTC
c. HV winding Temp High
d. LV winding Temp High
e. Main Tank PRD Opt
f. OLTC PRD Opt
g. Main tank oil Temp High
h. OLTC oil Temp High
6. O/C TW ( 51 TW-HS, 51 TW-LS)

Monday, April 25, 2011

END TO END TEST


END TO END TEST

1.The sending and receiving of datas from one end to other end is very importent in line protection
2.The Protection Signalling Equipment (PSE) is used in between both end protection panels.
3. Four main tripping signals are send and receive a) Distance protection b) Directional Earth Fault(DEF) c) Pole descripency second stage d) Breaker Failure second stage

Thursday, April 14, 2011

FOIP CONNECTIONS

Line diffrential protection
Relay to FOIP panel and FOIP to communication panel connection Drawing

380 KV RELAY SETTINGS

1.LINE DIFFRENTIAL - 1
2.LINE DIFFRENTIAL - 2
3. HIGH IMPEDENCE BB PRO
4. PD & BF
5. UNDER VOLTAGE RELAYS

TIMINGS

1. 380 kv breaker tripping time 14 -15 ms and closing time 78-79 ms
2. Breaker coil current a. Closing coil current 5-6 Amps b. Tripping coil current 13-14.5 Amps
3. PD first stage timeing 500 ms second stage 2.5 s
4. Breaker Filure first stage timeing 100 ms second stage 200 ms

Thursday, March 31, 2011

DESIGN TIP-2 A/R CLOSE

Auto reclose function 1. In 1-1/2 scheme auto reclose should close bus side breaker first and middle breaker secound. 2. The one more condition for close the middle breaker by A/R is the other two breakers should be in closed condition.

Sunday, March 27, 2011

380 KV GIS THOSHIBA

INTER LOCK FOR CIRCUIT BREAKER (GAS & HYDRAULIC OIL)

1. For tripping operation the HYDRAULIC OIL pressure must be 25.5 MPa and GIS gas pressure of the CB compartment should be 0.7 MPa . Breaker failure should be initiates If CB is failure to trip condition.

2. For closing operation the HYDRAULIC OIL pressure must be 27 MPa and GIS gas pressure of the CB compartment should be 0.725 MPa .

3. Normal condition Gas pressure CB 0.75 MPa, Gas pressure other compartment 0.6 MPa, Hydraulic Oil pressure 31.5 MPa

Saturday, February 19, 2011

Wednesday, February 16, 2011

KVS100 SYN RELAY CB INPUT

How to give CB input to KVAS100 SYN check relay to start the syn check function ?

LOGIC FUNCTION ----------- SCHEME Fn Links-1 -------- set 000000000100011

INPUT Start chsyn ------------00000001

48 DC voltage available in relay
Take +ve voltage connect with CB "b" contact (NC)
When CB is open relay will start the Syn function give permit to close the CB
Relay will reset when CB is closed.

FIBER OPTIC CABLES

FIBER OPTIC CABLES USED FOR LINE DIFFERENTIAL AND DRP PANEL

MAKE: OPTOKON CO . LTD

MULTIDUPLEX

J-V (ZN) H 2G 62.5/125 BLUE (2.8 mm) (850 nM)

PATCH CORD TERMINATION


Blog Archive

About Me

My photo
THIS IS SIVA T&C ENGINEER IN NCC LTD - SAUDI.