CABLE LAYING

BEFORE CABLE LAYING

1.There are two schedules

a. Laying schedule

b. Termination Schedule

2.Seperate the laying schedule in size vice for laying and gland calculations

3.Seperate the schedules in panel vice for termination and lug quantity

4.Compare the panel vice cable schedule with appropriate drawings

5.Keep at lest one spare core per cable.

6.Arange the following materials

a. Cable Jake

b. Cable rollers tools ext..

c. Cable cutter

d. White marker

e. Cello tape or masking tape and insulation tape

f. Aluminum ladder

g. Scrap cable sheath

h. Cable tie

download lugs manual

Monday, May 3, 2010

THE DISMANTLED PANELS

HOW TO HANDOVER THE DISMANTLED PANELS TO SEC-EOA

1. Take the list of Dismantled materials

2. Go to SEC and meet the particular department foreman and inform him that the list of

Materials we are taken out from the substation.

3. If he says ok the go to facility maintenance get the Gate pass form ( Form dounload here)

4. The gate pass is in ARABIC and it should be fillip in Arabic.

5. Mention the vehicle name and number driver name and iqma number

6. Driver must have the SEC ID or other vice arrange the temporary access

7. Vehicle must have the gate entry sticker or otherwise arrange temporary access.

8. Get the signature from the foreman in the gate pass and go to ISPD LMPD.

9. Now bring out the materials from station

10. Dismantled all parts and segregate

11. Make MDR (Material disposal request ( Form download )


About Me

My photo
THIS IS SIVA T&C ENGINEER IN NCC LTD - SAUDI.