Friday, December 24, 2010
TESTING TIPS -2
Monday, December 20, 2010
DESIGN TIP -1 CT CIRCUIT
Thursday, December 16, 2010
CT CIRCUIT
Monday, December 6, 2010
AC power panel Commissioning
Sunday, December 5, 2010
380 KV GIS HI POT TEST
Monday, November 8, 2010
Friday, October 15, 2010
Tips to test -1
Tuesday, June 29, 2010
Friday, May 14, 2010
CABLE LAYING
BEFORE CABLE LAYING
a. Laying schedule
b. Termination Schedule
2.Seperate the laying schedule in size vice for laying and gland calculations
3.Seperate the schedules in panel vice for termination and lug quantity
4.Compare the panel vice cable schedule with appropriate drawings
5.Keep at lest one spare core per cable.
6.Arange the following materials
a. Cable Jake
b. Cable rollers tools ext..
c. Cable cutter
d. White marker
e. Cello tape or masking tape and insulation tape
f. Aluminum ladder
g. Scrap cable sheath
h. Cable tie
Tuesday, May 4, 2010
Monday, May 3, 2010
THE DISMANTLED PANELS
HOW TO HANDOVER THE DISMANTLED PANELS TO SEC-EOA
1. Take the list of Dismantled materials
2. Go to SEC and meet the particular department foreman and inform him that the list of
Materials we are taken out from the substation.
3. If he says ok the go to facility maintenance get the Gate pass form ( Form dounload here)
4. The gate pass is in ARABIC and it should be fillip in Arabic.
5. Mention the vehicle name and number driver name and iqma number
6. Driver must have the SEC ID or other vice arrange the temporary access
7. Vehicle must have the gate entry sticker or otherwise arrange temporary access.
8. Get the signature from the foreman in the gate pass and go to ISPD LMPD.
9. Now bring out the materials from station
10. Dismantled all parts and segregate
11. Make MDR (Material disposal request ( Form download )
Friday, February 5, 2010
ABU HADRIYAH BSP
a. DTTR (21 relay)
b.Second stage PD trip from both breakers
Initiation
1.86-1, 2, 3, 4 (Transformer High Side)
2.86BF A609 (Transformer Low Side)
3.86BF A804,86BF A806
4.94-1,94-2 (line-1)
94 BF Stage-1
1. After 62BF-1 time Retrip A805
86 BF Stage-2 (2 Units)
After 62BF-2
2. Trip & Close black A804,A806
3. Trip & Close black A609 & A301
4. Trip & Close black other end Al fadhili through PSE
5. BF initiation A804,A806,A609
6. Trip save A805.
Breaker Failure for A804
Initiation
1.86-1, 2, 3, 4 (Transformer High Side)
2.86BF A609 (Transformer Low Side)
3.86BF A805,86BF A807, 86BF A810
4.86 BB-1,2 A804
94 BF Stage-1
7. After 62BF-1 time Retrip A804
86 BF Stage-2 (2 Units)
After 62BF-2
8. Trip & Close black A807,A810,A805
9. Trip & Close black A609 & A301
10. Bus -1 BB initiation (A807,A810)
11. BF initiation A807,A810,A805, A609
12. Trip save A804.